LESCO Project 132kV XLPE UNDERGROUND COPPER CABLE BETWEEN 132KV SUNNY VIEW GRID STATION and 132KV MCLEOD ROAD GRID STATION (Turnkey Project)

LOT –I (2.1KM) & LOT –II (3.9KM)

  • Description: Procurement plant, design, supply, installation, laying, testing and commissioning of 132kv XLPE underground copper cable 1000mm² and Fiber optic between 132kv Sunny view grid station – 132kv Mc Leod road grid station (2.1km) under lot-I & 132kv Mc Leod road grid station – 132kv Qartaba grid station (3.9km) under lot-II on turnkey basis under ADB loan no. 3096-pak (tranche-iv).
  • Contract No. ADB-TRANCHE-IV-LESCO-02(S)-2016
  • Location: Lahore, Pakistan
  • Client: LESCO
  • Status: LOT -1 Completed
  • LOT -2 Ongoing